Here you will find a list of all major road work projects under way in the Town.

Crestwood Reconstruction

The Town of Montreal West will be rebuilding the infrastructure on Crestwood.

Project scope

  • Excavation and foundation work
  • Replacement of sewer main
  • Replacement of water main
  • Replacement of concrete sidewalks and asphalt street surface

Schedule

  • It is expected that the project will commence the week of April 29th, 2019. Temporary water lines will be installed and connected to all the affected homes. Excavation work will begin the following week.
  • The entire project is expected to be completed by mid-September.
  • During this time, affected sections of the street being worked on will be closed to traffic, especially during the day. Access for emergency vehicles will be maintained at all times

Drinking water

  • A temporary aqueduct will be installed to provide potable water. Please avoid contact with the temporary water pipes to ensure service is not disrupted.

Project management

  • A Town-employed representative will be on the construction site at all times. The project will be supervised by engineering firm Avizo Experts Conseils Inc.
  • You can call or email Public Works during regular business hours (from Monday to Friday, 7:30 a.m. to 4:30 p.m.) to be put in touch with the project supervisor.
  • If there is an exceptional emergency situation related to the construction project outside of the regular business hours, please contact Public Security Dispatch at (514) 630-1234 for assistance or 911 for emergency services.